Clark County, Illinois: solar, wind, and storage projects and permits
Proposed projects, county offices, and the state rules for a solar, wind, or battery storage project in Clark County, county seat Marshall.
Check land in Clark CountyOpens the land report with the map on the county; click a spot for its flood, wetland, habitat, line-distance and parcel check.
What energy projects are proposed in Clark County?
The MISO interconnection queue lists 8 proposed projects in Clark County (4 solar, 1 solar plus storage, 3 battery storage), about 1,259 MW in all. 4 have a signed interconnection agreement.
What stands out in Clark County
By capacity, solar leads in Clark County with 500 MW across 4 projects, followed by solar paired with storage (1 project, 409 MW) and battery storage (3 projects, 350 MW). The largest is queue number J1263, a 409 MW solar paired with storage request in the MISO queue, agreement signed, filed Apr 2019, with a target in-service date of Jan 2022. Of the 8, 4 are still in study, 3 have a signed agreement and 1 is under construction. All of them are in the MISO queue, which covers the Ameren Illinois side of the state. The requests were filed between Mar 2018 and Apr 2024. Target in-service dates for those not yet under construction span Jan 2022 to Sep 2028; 5 of them have already passed, which means those schedules slipped.
A listing means a developer asked the grid operator to study connecting a project; many are never built, and the status column says where each one stands.
Reading the table: the queue number is the operator's ID for the request (MISO J-numbers, PJM AE/AF/AG-numbers); operators do not publish developer names in these files. Connection is the transmission owner and, where listed, the substation or line; "Other_" is the operator's own placeholder. In study (Phase 1/2) are MISO's definitive-planning study phases; "moved to TC1" means a PJM request was carried into Transition Cycle 1; "CIR Increase" is a request to add capacity rights to an existing project; "LRTP" names a MISO long-range transmission project. For PJM rows, MW is the figure in the megawatt column of PJM's public queue export; PJM also tracks maximum facility output and capacity rights separately, so a project's study documents can show a different number. 5 target in-service dates below have already passed while the request is still open: operators keep the developer's last reported date until the developer changes it, so a past date means the schedule slipped, not that the project was built.
Scroll the table sideways to see every column.
| Queue number and connection | Type | MW | Stage | Requested | Target in-service iThe in-service date the developer gave the grid operator. Developers set and change it, many projects slip, and some are never built. |
|---|---|---|---|---|---|
| J1180MISO · Ameren Illinois · Casey West - Sullivan 345 kV Line | Solar | 75 | Under construction | Mar 2018 | Aug 2020 |
| J1263MISO · Ameren Illinois · Casey - Kansas West 345kV Line | Solar + storage | 409 | Agreement signed | Apr 2019 | Jan 2022 date passed; status per the operator |
| J1382MISO · Ameren Illinois · Hutsonville - Neoga 138 kV Line tap | Solar | 150 | Agreement signed | Apr 2019 | Aug 2022 date passed; status per the operator |
| J1475MISO · Ameren Illinois · Casey West - Sullivan 345 kV Line Tap | Solar | 75 | Agreement signed | Apr 2019 | Apr 2022 date passed; status per the operator |
| J3256MISO · Ameren Illinois · 4GALLATIN - 4KANSAS 138.0kV | Solar | 200 | In study (Phase 2) | Apr 2024 | Sep 2028 |
| J2170MISO · Ameren Illinois · Snyder 345 kV (J1180/J1475 POI) | Storage | 150 | In study (Phase 2) | Apr 2022 | Jan 2024 date passed; status per the operator |
| J3695MISO · Ameren Illinois · 7CASEY - 7SNYDER 345.0kV | Storage | 150 | In study (Phase 2) | Apr 2024 | Sep 2028 |
| J2159MISO · Ameren Illinois · Hutsonville - Neoga 138KV | Storage | 50 | In study (Phase 2) | Aug 2021 | Aug 2024 date passed; status per the operator |
Sources: MISO generator interconnection queue and PJM interconnection queue, downloaded October 7, 2026; withdrawn and operating projects are left out, and the operators do not publish developer names. What the stages mean.
What can Clark County require of a project?
Illinois law sets the ceiling: Clark County must approve a commercial wind or solar project that meets the state standards, must finish its public hearing within 60 days, and may not ban them in agricultural or industrial zones (55 ILCS 5/5-12020); battery storage has had its own statewide standards since June 1, 2026 (55 ILCS 5/5-12024). Land inside a city or village falls under municipal zoning instead.
Recent local action: On June 18, 2026 the Clark County Board voted 5–0 (two members absent) to issue a building permit for Moonshine Solar's commercial solar energy facility and to approve a memorandum of understanding with Snider Solar LLC for a 30 MWac commercial solar facility, with conditions including no battery storage on site and a road use agreement before construction. (Clark County Board minutes, June 18, 2026)
State siting standardsFarmland agreement (AIMA)Property taxes
Who to contact in Clark County
Assessment questions go to the supervisor of assessments, special use applications to the zoning office, and road use agreements to the county engineer; the county seat is Marshall. A drainage district, if the land is in one, must receive the developer's drainage plan.
Clark County websiteSupervisor of assessmentsCounty engineer and highways
Solar for homes and businesses in Clark County
Illinois net metering, the Illinois Shines incentive, and HOA rules are the same statewide; Ameren Illinois sets the application steps here: Illinois home and business solar rules · utility application links.
State and federal reviews
Illinois EPA stormwater coverage, IDNR's EcoCAT review, historic preservation review, and federal wildlife screening can apply to a site in Clark County: Illinois agency list.